India, July 29 -- The Government of India has issued a release:
The present installed nuclear power capacity in the country is 8,780 MW comprising of
Location
Project
Capacity (MW)
Physical Progress/ Status
Expected Date Of Commissioning
Projects Under Construction / Commissioning
In advanced stage of commissioning (expected to be operational in 2026)
Kudankulam, Tamilnadu
KKNPP-3&4
2 X 1000
82.65 %
June-2027/ June-2028
KKNPP- 5&6
2 X 1000
45.00 %
June-2029/ March-2030
Completion of construction and commissioning is expected to be completed in about 6 years from First Pour of Concrete.
Kaiga, Karnataka
KAIGA-5&6
2 X 700
June-2031/ June-2032
TAPS-1
160
TAPS-2
160
TAPS-3
540
TAPS-4
540
RAPS-2
200
RAPS-3
220
RAPS-4
220
RAPS-5
220
RAPS-6
220
RAPS-7
700
Kalpakkam
MAPS-1
220
MAPS-2
220
Kudankulam
KKNPP-1
1000
KKNPP-2
1000
Uttar Pradesh
Narora
NAPS-1
220
NAPS-2
220
KAPS-1
220
KAPS-2
220
KAPS-3
700
KAPS-4
700
KGS-1
220
KGS-2
220
KGS-3
220
KGS-4
220
24 nuclear power plants, contributing about 3.1% in 2025-26 in total electricity generation. The details are tabulated in Annexure.
(as of June 2026)
Rajasthan
RAPP-8
1 X 700
96.26 %
FPC will start after completion of ground improvement works of Nuclear Island.
The Government has drawn up a roadmap for reaching the 100 GW nuclear power capacity by 2047, as announced in the Nuclear Energy Mission. As per the roadmap, the present nuclear power capacity of 8.78 GW is expected to reach about 22 GW by 2031-32. Another 32 GW of nuclear power capacity is envisaged to be set up under NPCIL beyond 2032 which will comprise of indigenous Pressurised Heavy Water Reactors (PHWRs) and Light Water Reactors (LWRs). Additionally, the Government has approved the pre-project activities of 2 x 500 MW FBR 1 & 2, to be built with the same design as of PFBR of Kalpakkam. The balance of 45 GW comprising of reactors of different technologies, is expected to be set up by other Public Sector Enterprises (Central & State), Private sector and Joint Ventures in different business models.
Maharashtra
Tarapur
Tamilnadu
Gujarat
Kakrapar
Karnataka
Kaiga
Highest priority is accorded to safety in all aspects of nuclear power viz. siting, design, construction, commissioning, and operation. Nuclear power plants are designed adopting safety principles of redundancy, diversity and provided fail-safe design features following an overlapping defence-in-depth approach, in line with codes and guides of Atomic Energy Regulatory Board (AERB). There is a robust regulatory mechanism of safety reviews at multiple levels. The safety of nuclear power plants is continuously monitored and reviewed by the AERB. Required fuel security is ensured by Nuclear Fuel Complex, a constituent unit of Department of Atomic Energy, Government of India.
Rajasthan
Rawatbhata
The Government has announced a Nuclear Energy Mission to reach a capacity of 100 GW nuclear power capacity by 2047 and formulated a roadmap for the same. The Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Act 2025 enables wider participation in the nuclear power sector, both from public and private sector.
Gorakhpur, Haryana
This information was given by Union Minister of State for Prime Minister's office and Personnel, Public Grievances and Pensions, Atomic Energy and Space, Dr. Jitendra Singh, in a written reply in the Lok Sabha today.
GHAVP-1&2
2 X 700