India, Aug. 5 -- The Government of India has issued a release:

The Government has announced an ambitious Nuclear Energy Mission for Viksit Bharat with a target of reaching a nuclear power capacity of 100 GW by 2047. Nuclear Power Projects are having a Project/ Construction period of 10-12 years. No specific Nuclear Power Projects have been sanctioned after the Middle East conflict.

Nuclear Power Projects under Construction/ Commissioning

Location & State

Project

Capacity

Expected Completion Date/

Indigeneous/

Rawatbhata, Rajasthan

RAPP-8

1 X 700

Unit-8 is in advanced stage of commissioning (expected to

Indigeneous

Gorakhpur, Haryana

GHAVP

2 X 700

Completion of construction and commissioning is expected to be completed in about 6 years from First Pour of Concrete.

Indigeneous

Kudankulam, Tamilnadu

KKNPP-3&4

2 X 1000

June-2027/ June-2028

Foreign Technology

KKNPP-5&6

2 X 1000

June-2029/ March-2030

Foreign

Kalpakkam,

PFBR

1 X 500

Attained criticality on 06.04.2026

Indigeneous

Kaiga, Karnataka

KAIGA-5&6

2 X 700

June-2031/ June-2032

Indigeneous

Projects Under Pre-project Activities

Gorakhpur,

GHAVP-

2 X 700

Indigeneous

Chutka, Madhya

Chutka-1&2

2 X 700

Indigeneous

Mahi Banswara, Rajasthan

Mahi

2 X 700

Indigeneous

Mahi

2 X 700

Indigeneous

Kalpakkam,

FBR 1& 2

2 X 500

Indigeneous

Planned Nuclear Power Projects/ Sites

Rawatbhata,

RAPP-9&10

2 X 700

Indigeneous

Kakrapar, Gujarat

KAPP-5&6

2 X 700

Indigeneous

Narora, Uttar

NAPP-3&4

2 X 700

Indigeneous

Jaitapur,

JNPP-1 to 6

6 X 1730

Foreign

Kovvada,

Kovvada-

6 X 1208

Foreign

Haripur,

Haripur-

6 X 1000

Foreign

Mithi Virdi, Gujarat

Mithi Virdi-

6 X 1000

Foreign

Bhimpur,

Bhimpur-

4 X 700

Indigeneous

The details of Nuclear Power Projects under various stages of implementation and those planned are tabulated in Annexure.

(MW)

Status

Foreign Technology

be operational in 2026).

1&2

Technology

Tamilnadu

Haryana

3&4

Pradesh

Banswara-1&2

Banswara 3&4

Tamilnadu

Rajasthan

Proposed Nuclear Power Projects

Pradesh

Maharashtra

Technology

Andhra Pradesh

1 to 6

Technology

West Bengal

1 to 6

Technology

1 to 6

Technology

Madhya Pradesh

1 to 4

There have been apprehensions in a section of the people at few sites, about safety of the site & plant, issues related to Rehabilitation, and fears of loss of traditional means of livelihood like fishing and horticulture. The apprehensions have been addressed through public awareness programmes adopting a multipronged approach in a credible manner. Highest priority is accorded to safety in all aspects of nuclear power viz. siting, design, construction, commissioning, and operation. Further, safety is not static and improvements/ upgrades are effected in nuclear power plants based on evolving global standards, events and operating experience feedback.

This information was given by Union Minister of State for Prime Minister's office and Personnel, Public Grievances and Pensions, Atomic Energy and Space, Dr. Jitendra Singh, in a written reply in the Lok Sabha today.

Disclaimer: Curated by HT Syndication.