India, March 19 -- The Government of India has issued a release:
Location
Project
Capacity (MW)
Projects Under Construction / Commissioning
Rajasthan
RAPP-8
700
Kudankulam, Tamilnadu
KKNPP-3&4
2 X 1000
KKNPP-5&6
2 X 1000
Gorakhpur, Haryana
GHAVP-1&2
2 X 700
Kaiga, Karnataka
Kaiga-5&6
2 X 700
PFBR, Kalpakkam
PFBR
1 X 500
Projects Under Pre-project Activities
Gorakhpur, Haryana
GHAVP-3&4
2 X 700
Chutka, Madhya Pradesh
Chutka-1&2
2 X 700
Mahi Banswara, Rajasthan
Mahi Banswara-1&2
2 X 700
Mahi Banswara-3&4
2 X 700
The present installed nuclear power capacity in the country is 8,780 MW comprising of 24 nuclear power plants (excluding RAPS-1 - 100 MW).
The total generation from the nuclear power plants during the past three years have been 45855 Million Units (MUs) in 2022-23, 47971 MUs in 2023-24 and 56681 Mus in 2024-25.
At present, there are 18 nuclear power reactors with a total capacity of 13600 MW under implementation, comprising of 10 nuclear reactors under construction (including PFBR - 500 MW) and 8 reactors under pre-project activities.
BHAVINI is currently commissioning a 500 MWe Prototype Fast Breeder Reactor (PFBR) project at Kalpakkam, Tamil Nadu. Government has accorded approval to carry out pre-project activities for 2 x 500 MWe twin unit of FBR 1&2 project at Kalpakkam, Tamil Nadu. On attaining first criticality of PFBR, Government will be approached for financial sanction of FBR 1&2 projects.
This information was given by Union Minister of State (Independent Charge) for Science & Technology and Earth Sciences, and Minister of State in the Prime Minister's Office, Personnel, Public Grievances and Pensions, Atomic Energy and Space, Dr. Jitendra Singh, in a written reply in the Rajya Sabha on Thursday.
Disclaimer: Curated by HT Syndication.