India, March 13 -- The Government of India has issued a release:

Period

Outlay

2009-14

Rs. 838 Cr./year

2025-26

Rs. 10,599 Cr. (Nearly 13 times)

Period

New Track Commissioned

Average Commissioning of new tracks per year

2009-14

267 Km

53 Km

2014-25

2,150 Km

195 Km

Category

No of sanctioned Projects

Total Length

Length Commissioned till Mar'25  (in Km)

Total Exp upto Mar'25

New Lines

19

1,544

256

6,270

Doubling/Multi-tracking

30

2,466

1,173

21,773

Total

49

4,010

1,429

28,043

SN

Name of Project

Cost

1

Daitari-Banspani New Line and Jakhapura-Haridaspur 3rd Line (179 Km)

1,317

2

Jharsuguda - Sardega New Line (50 Km)

1,598

3

Haridaspur-Paradeep New Line (82 Km)

2,397

4

Angul-Sukinda New Line (104 Km)

2,834

5

Champa-Jharsuguda 3rd Line (152 Km)

1,227

6

Sambalpur-Titlagarh Doubling (182 Km)

2,262

7

Rourkela-Jharsuguda 3rd Line (101 Km)

1,313

8

Banspani-Daitari-Tomka-Jakhapura Doubling (164 Km)

1,827

9

Sambalpur-Talcher Doubling (174 Km)

1,539

10

Raipur - Titlagarh Doubling (203 Km)

1,171

11

Jharsuguda-Sardega Doubling (50 Km)

3,200

SN

Name of Project

Total Cost  (In Crores of Rs.)

1

Junagarh-Nabarangpur New Line (116 Km)

2,865

2

Nabarangpur-JeyporeNew Line (41 Km)

748

3

Jeypore-Malkangiri New Line (130 Km)

2,344

4

Malkangiri - Pandurangapuram New Line (174 Km)

3,592

5

Buramara-Chakulia New Line (60 Km)

1,459

6

Gunupur-Therubali New Line (74 Km)

1,166

7

Puri - Konark New Line (32 Km)

492

8

Badampahar-Kendujhargarh New Line (82 Km)

1,876

9

Bangriposi-Gorumahisani New Line (86 Km)

2,269

10

Bargarh Road-Nawapara Road New Line     (138 Km)

2,622

11

Vizianagram-Titlagarh 3rd Line (265 Km)

6,996

12

Jarapada- Budhapank 3rd& 4th Line with flyover at Talcher (101 Km)

810

13

Budhapank- Salegaon via Rajatgarh 3rd& 4th Line (170 Km)

2,023

14

Nergundi - Vizianagaram 3rd Line (385 Km)

4,963

15

Kottavalasa-Koraput Doubling (189 Km)

2,500

16

Koraput-Singapur Road Doubling (165 Km)

2,362

17

Jagdalpur-Koraput Doubling (107 Km)

1,547

18

Jharsuguda-Bilaspur 4th line (206 Km)

2,596

19

Bondamunda-Ranchi Doubling (159 Km)

3,029

20

Narayangarh-Bhadrak 3rd line (153 Km)

2,136

21

Bhadrak-Nergundi 3rd Line (92 Km)

1,284

SN

Activity

Scope

Status

1

Tunnel

7 nos (11.96 Km)

6 nos completed (7.7 Km).Works taken up in balance 1 tunnel

2

Important Bridge

5

All completed

3

Station Building

5

Works have been taken up

SN

Train No & Name

1

18515/18516 Kirandul - Visakhapatnam Express

2

58501/58502 Kirandul - Visakhapatnam Passenger

3

58537/58538 Koraput - Visakhapatnam Passenger

SN

Train No & Name

1

16107/16108 Tambaram - Santragachi Amrit Bharat Express

2

16597/16598 SMVT Bengaluru - Alipurduar Amrit Bharat Express

3

16523/16524 SMVT Bengaluru - Balurghat Express

4

16223/16224 SMVT Bengaluru - Radhikapur Express

5

17015/17016 Secunderabad - Bhubaneswar Visakha Express

6

18045/18046 Charlapalli - Shalimar East Coast Express

(More than 3.5 times)

NL/GC/DL

(Rs. in Cr)

(In Crores of Rs.)

(in Km)

Railway has taken up infrastructure upgradation in Odisha in a big way.

Railway Budget:

Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Odisha is as under: 

Track Construction:

The details of commissioning/laying of new track falling fully/partly in the State of Odisha during 2009-14 and 2014-25 is as under: 

 Project Sanctioned:

As on 01.04.2025, 49 projects (19 New Lines and 30 Doubling), of a total length of 4,010 Km, costing Rs. 67,496 crore, falling fully/partly in Odisha, are sanctioned, out of which 1,429 km length has been commissioned and an expenditure of Rs.28,043 crore has been incurred upto March' 2025. The summary is as under:-

 Recently Completed Projects:

Details of some of the recently completed projects falling fully/partly in Odisha are as under:

 Ongoing Projects:

Further, some of the main projects falling fully/partly in Odisha which have been taken up are as under: 

 The progress of some of the major projects is as under:

1. Khurda Road-Bolangir (301 Km) new line: The latest cost of the project is Rs.5,089 crore. Expenditure of Rs.4,311 crore has been incurred on this project upto March, 2025. An outlay of Rs.1938 crore has also been provided in the financial year 2025-26. Status of project is as under:-

Status of Daspalla - Purunakatak (75 km) is as under:- 

 2. Construction of 3rd and 4th line between Salegaon- Budhapank(85 Rkm): The work has been taken up. Status is as below:-

 Sanction of any railway project depends upon many parameters/factors which include the following:

 Completion of Railway project/s depends on various factors which include the following:

All these factors affect the completion time and cost of the project/s.

Presently, Bhubaneswar-Rayagada-Jeypore-Koraput sector is being served by the daily service of 18447/18448 Bhubaneswar-Jagdalpur Hirakhand Express. Moreover, Koraput is connected to Kottavalasa by 03 pairs of train services while Kottavalasa is further connected to Bhubaneswar by 06 pairs of train services. These train services are listed below:

Trains serving Koraput-Kottavalasa sector:

 Trains serving Kottavalasa- Bhubaneswar sector:

This information was provided by the Union Minister for Railways, Information & Broadcasting and Electronics & Information Technology, Shri Ashwini Vaishnaw, in a reply to a question in Rajya Sabha today.