India, Dec. 17 -- The Government of India has issued a release:
Waste to Energy Programme
CFA in Rs Crore
Biogas generation
Rs 0.25 Crore per 12000cum/day
BioCNG generation
Rs 4.0 Crore per 4800 kg/day (for BioCNG generation from new biogas plant)
Power generation based on Biogas
Rs 0.75 Crore/MW (for power generation from new biogas plant)
Power based on bio & agro-industrial waste
Rs 0.4 Crore/MW
Biomass Gasifier
Rs. 2,500 per kWe with dual fuel engines for electrical application
Biomass Programme
CFA
Briquette manufacturing plants
Rs. 9.00 Lakhs/ TPH
Non-Torrefied Pellet manufacturing plant
Rs. 21 lakhs/MTPH production capacity or 30% of the capital cost considered for plant and machinery of 1 TPH plant, whichever is lower (Maximum Rs. 105 lakhs per project)
Torrefied Pellet manufacturing plant
Rs. 42 lakhs/MTPH production capacity or 30% of the capital cost considered for plant and machinery of 1 TPH plant, whichever is lower (Maximum Rs. 210 lakhs per project)
Non-Bagasse Cogeneration Projects
Rs. 40 Lakhs/ Megawatt
Biogas Programme
CFA
For small biogas plants (1-25 cubic meter/day plant capacity):
Rs. 9,800/- to Rs. 70,400/- per plant based on size of the plant in cubic meter
For Power generation and thermal application (25 - 2500 cubic meter/day plant capacity):
Rs. 35,000/- to Rs. 45,000/- per kilowatt for power generation
Biomass Projects
Waste to Energy Projects
Biogas Plants
Sl No
State
Capacity (MW)
Capacity (MWe)
Nos
1
Andhra Pradesh
35.1
35.95
28505
2
Arunachal Pradesh
0
0
349
3
Assam
2
0
23612
4
Bihar
39.8
0.32
236
5
Chhattisgarh
54
0
11030
6
Goa
0
1
140
7
Gujarat
12
15.2
5427
8
Haryana
87.4
17.39
3487
9
Himachal Pradesh
1.5
0
294
10
Jharkhand
14.8
1.04
545
11
Karnataka
536.81
8.41
34657
12
Kerala
1.55
0.23
9639
13
Madhya Pradesh
31.2
5.86
32120
14
Maharashtra
1073.5
24.26
71653
15
Manipur
0
0
25
16
Meghalaya
0
0
867
17
Mizoram
0
0
648
18
Nagaland
0
0
102
19
Odisha
0.6
0
5966
20
Punjab
140.29
21.77
19288
21
Rajasthan
19.85
1.19
2404
22
Sikkim
0
0
170
23
Tamil Nadu
112.55
8.68
1740
24
Telangana
4.03
9.79
11159
25
Tripura
0
0
546
26
Uttarakhand
12.5
6.89
8362
27
Uttar Pradesh
146.6
41.34
3594
28
West Bengal
31.6
4.06
851
29
Andaman and Nicobar Islands
0
0
0
30
Chandigarh
0
0
0
31
Dadra and Nagar Haveli and Daman & Diu
3.75
0
18
32
NCT of Delhi
0
24.17
0
33
Jammu & Kashmir
0
0
101
34
Ladakh
0
0
0
35
Lakshadweep
0
0
0
36
Puducherry
0
0
0
37
Others
0
0
10544
Total
2361.43
227.56
288079
Rs 3.0 Crore per 4800 kg/day (for BioCNG generation from existing Biogas plant)
Rs 0.5 Crore/MW (for power generation from existing Biogas plant)
Rs. 15,000 per kWe with 100% gas engines for electrical application
(Maximum CFA- Rs. 45.00 Lakh per project).
Maximum CFA- Rs. 5.00 Crore per project).
Rs. 17,500/- to Rs. 22,500/- per kilowatt equivalent for thermal applications.
Rs. 2 lakh per 300 kWth for thermal applications
Note: 20% higher than Standard CFA in for NER, Island, Registered Gaushalas and SC/ST beneficiaries);
Ministry of New and Renewable Energy supports installation of Bioenergy Projects in the country under National Bioenergy Programme (NBP), Phase-I, which was notified on 02.11.2022, with a budget outlay of Rs. 998 Crore, for the period 2022-23 to 2025.26. The details of Central Financial Assistance (CFA) provided is given at Annexure-I.
During the last ten years, the Government has been supporting Bioenergy Projects through various Schemes, namely National Biogas and Manure Management Programme (NBMMP) during 12th Five Year Plan, New National Biogas & Organic Manure Programme (NNBOMP) from 2018-19 to 2020-21, Scheme to support promotion of Grid interactive Biomass Power and Bagasse cogeneration in sugar mills during 12th Plan Period, Programme on Energy from Urban, Industrial and Agricultural Wastes /Residues during 12th Plan period, Scheme to support Promotion of Biomass based Cogeneration in Sugar Mills and other Industries in the Country from 2018-19 to 2020-21.
The details of bioenergy projects installed in the country during the last ten years, State-wise, is given at Annexure-II. Further, new bioenergy projects are being promoted under the NBP Phase-I.
Annexure-I
The existing CFA Support for setting up of Bioenergy Projects in the country under National Bioenergy Programme is given as under:
Annexure-II
REFERRED TO IN REPLY TO THE LOK SABHA UNSTARRED QUESTION NO. 2809, Part (d) TO BE ANSWERED ON 17.12.2025 on 'Financial Assistance for Bio-Energy Programme'.
The details of bioenergy projects installed in the country during the last ten years is given as under:
Disclaimer: Curated by HT Syndication.