GUWAHATI, India, April 1 -- Gauhati High Court issued the following order on Feb. 27:

1. The instant writ petition is filed by the petitioner challenging the non-payment of the admitted amount of Rs.10,08,000/- by the Respondent Authorities to the petitioner for the works executed by the petitioner.

2. The case of the petitioner herein is that the petitioner has been allotted the works vide work orders dated 17.06.2015, 02.05.2015 and 07.02.2018 issued by the respondent No.2. The total value of the allotted works was Rs. 1,36,52,000/-. Accordingly, the petitioner completed the allotted works. It is the further case of the petitioner that thereafter Respondent Authorities inspected and verified the works and issued the completion certificate on 08.08.2018 against the works executed by the petitioner. The petitioner was paid Rs. 1,26,44,000/- out of total bill amount of Rs. 1,36,52,000/- wherein Rs. 10,08,000/- remained outstanding which is due to be paid to the petitioner. But no action has been taken by the Respondent Authorities to release the outstanding bill amount of Rs. 10,08,000/- to the petitioner. Hence, this petition.

3. The learned counsel appearing on behalf of the petitioner submitted that the petitioner has been pursuing the matter diligently with the respondents, but the Respondent Authorities have not shown any interest in making the payment of the admitted amount of Rs. 10,08,000/- due to the petitioner for which the petitioner is facing hardship. The learned counsel for the petitioner further submitted that the Respondent Authorities have failed to discharge their duty in accordance with law and the same has caused prejudice to the petitioner. Hence, the petitioner has approached this Court by filing the instant writ petition.

4. An affidavit-in-opposition has been filed by the respondent No.4, i.e. the Registrar of Co-operative Societies, Assam, Khanapara wherein it is stated that there is a liability of Rs.15,62,447.93 against Paschim Sarukhetri GPSS Ltd. In Barpeta District and all other liabilities with respect to the godowns of Dakshim Dharmapur and Natum Dehar Mouza BSS Ltd. under Nalbari District, Barshilajhar SS Ltd., Dakua SS Ltd. & Sekhar SS Ltd under Udalguri District has been met up and hence the concerned amounts are already released to HOUSEFED. It is further stated in the said affidavit-in-opposition that the amount would be released to the petitioner upon approval of sanction from the sanctioning authority as well as allotment of funds required from the Government.

5. Upon perusal of the materials on record, and more particularly the affidavit-in-opposition filed by the respondent No.4, it would be seen that the Respondents therefore admit that the petitioner is entitled to the amount of Rs. 10,08,000/-.